It is still on how to use Microsoft Project. Today, I will be teaching you how to assign resources. Resources are the materials workers need to complete given tasks.

Resources cannot be assigned except tasks are identified. Resources are categorized into four type: Work (people or equipment), Material (paper, ink, toner, etc), Cost (airfare, lodging) and Budget (project-level work, material and cost resources).

To enter resources, follow these steps:

From the View tab, choose Resource Sheet.

step-1

Enter the details, as desired.

step-2

But for you to assign resources, you have to:

In the Gantt Chart view, under the Resource Names column, select the appropriate resource(s) that has been assigned to the task.

step-2b

Your questions are welcome.