For project to correctly determine a schedule, working and non-working times should be included. Project has three default base calendars – Standard (traditional), 24 Hours and Night Shift. Each base calendar can be customized to meet your needs.
- To create a calendar, kindly follow the steps below:
- From the Project Tab, click Change Working Time.
- Click Create New Calendar
- Enter a name for the Calendar; Select a Type and Click OK
- Specify exceptions (holidays, non-working days/hours). Then click OK.
After yo u have done the above, then ensure you assign the calendar to a project.
To do this, kindly follow these two steps:
- From the Project tab, click Project Information.
- Select the desired calendar from the “dropdown” list and click OK.