For project to correctly determine a schedule, working and non-working times should be included. Project has three default base calendars – Standard (traditional), 24 Hours and Night Shift. Each base calendar can be customized to meet your needs.

  1. To create a calendar, kindly follow the steps below:
  2. From the Project Tab, click Change Working Time.
  3. Click Create New Calendar
  4. Enter a name for the Calendar; Select a Type and Click OK
  5. Specify exceptions (holidays, non-working days/hours). Then click OK.

After yo u have done the above, then ensure you assign the calendar to a project.

To do this, kindly follow these two steps:

  1. From the Project tab, click Project Information.
  2. Select the desired calendar from the “dropdown” list and click OK.

 

 

Your questions are welcome.